When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS.

You can update these changes to the integration journal to keep the bid rates and bid values intact.


Project manager Project manager Start Start Review bid rate and bid value Review bid rate and bid value WBS calculation updates the bid rate and bid value for each task.The relevant calculations are:Bid value = Calculated value + Contingency + IndexCalculated value = sum of Total sales prices of all estimate lines for the taskBid rate = Bid value / Forecast quantity in Scheduled unitCalculated rate = Calculated value / Forecast quantity in Scheduled unitYou can manually change the bid rate and bid value. If you do so, these are automatically locked.If the bid rate and bid value are locked and you run the WBS calculation:The bid rate and bid value aren't changed if: Prices are changed.You add a contingency.You apply an index.The bid value is changed if quantities are changed on a task. In this case, the locked bid ratio is used to calculate the new bid value.You can unlock the bid rate. To do so, on the Advanced WBS page, on the calculation fast tab, clear the Lock bid rate check box. Procedure 1. Click Advanced project management. 2. Click Project quotation. 3. In the list, click the link in the selected row. 4. Click Advanced WBS. 5. Click Edit. 6. Select an activity. 7. Click the Calculation tab. 8. In the Bid value field, enter a number. 9. In the Bid rate field, enter a number. 10. Click Save. 11. Usually, you run the WBS calculation for the whole WBS. To do so, select the root node (project) of the WBS. You can run the WBS calculation for another node. 12. Click Run WBS Calculation. 13. Click Save & Close. Update integration journal Update integration journal When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS.You can update these changes to the integration journal to keep the bid rates and bid values intact. Procedure 1. Click Advanced project management. 2. Click Project quotation. 3. In the list, click the link in the selected row. 4. Click Advanced WBS. 5. Click Edit. 6. Click Integration. 7. Click Update. 8. Click Save & Close. Notes For each integration journal line, you can find the updated bid rates and values on the Calculations tab. End End

Activities

Name Responsible Description

Review bid rate and bid value

Project manager

WBS calculation updates the bid rate and bid value for each task.


The relevant calculations are:

  • Bid value = Calculated value + Contingency + Index
  • Calculated value = sum of Total sales prices of all estimate lines for the task
  • Bid rate = Bid value / Forecast quantity in Scheduled unit
  • Calculated rate = Calculated value / Forecast quantity in Scheduled unit


You can manually change the bid rate and bid value. If you do so, these are automatically locked.

If the bid rate and bid value are locked and you run the WBS calculation:

  • The bid rate and bid value aren't changed if:
    • Prices are changed.
    • You add a contingency.
    • You apply an index.
  • The bid value is changed if quantities are changed on a task. In this case, the locked bid ratio is used to calculate the new bid value.

You can unlock the bid rate. To do so, on the Advanced WBS page, on the calculation fast tab, clear the Lock bid rate check box.

Update integration journal

Project manager

When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS.

You can update these changes to the integration journal to keep the bid rates and bid values intact.

Provide feedback